Demolition is completed and reconstruction begins, one month and one day after demolition began. Working two 12-hour shifts seven days a week, strongly motivated crews completed the job, almost four weeks ahead of the aggressive eight -week schedule and months ahead of what would have been the normal schedule. Reconstruction begins with the concrete being placed for the first new structural columns.